In 1902, the total cost was estimated at $35,000, which included $5,000 for a new heating system for the entire campus.

In 1903, the estimated cost was $25,000, without furnishings.

Total cost of the project: $26,205.16.

The projected completion date was January 1, 1904.
Actual completion date: February 12, 1904.